A software company sets up $m$ number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of m is equal to:
- (1)
150
- (2)
180
- (3)
160
- (4)
125
Show answer
Option (1) is correct.
Key from source paper